Contract sum turnover
QAR 53.00M
Base QAR 50.0M + variation 3.0M
Commercial cost control · Quantity surveying
Every month a quantity surveyor rebuilds the same commercial report by hand. Because it looks backward, problems surface in the final account, too late to act. This project automates that report and adds a forecast-margin layer that recalculates the outturn every month, turning cost control into an early-warning system.
Cost-Value Reconciliation live to the data date. Drag the reporting period to recalculate every KPI and chart. All figures QAR · synthetic.
Contract sum turnover
QAR 53.00M
Base QAR 50.0M + variation 3.0M
Forecast cost EAC
QAR 48.92M
vs budget 48.02M
Forecast margin
QAR 4.08M
4,077,325 absolute
Forecast margin % Below target
7.69%
Target 10.00% · −2.31pp
Cost variance vs budget
−QAR 0.90M
Net of contingency draw-down
Contingency remaining
QAR 0.00M
0% of QAR 1.35M reserve
Value certified to date
QAR 29.43M
56% of contract value
Project-total margin recalculated for every reporting month 1–20.
Cumulative position to the data date.
Packages forecast over budget at the current data date, worst first.
| Package | Budget | Forecast (EAC) | Variance | Var % | Flag |
|---|
✓ No packages flagged — the commercial book is on budget at this data date.
A synthetic project engineered to fail in three instructive ways, so the model can prove it catches them.
The model tracks a G+8 reinforced-concrete residential building in Doha: 9,500 m² GFA, 64 apartments, an 18-month programme (forecast to finish in 20), and a QAR 50M contract sum that grows to 53M after a client variation. Three problems were designed into it.
Month 2 · Absorbed
Substructure slips a month; +QAR 0.45M of works and extended prelims. Soaked up by contingency, so margin is untouched, the reserve does its job.
Month 7 · Dilutive
A QAR 3.0M scope addition priced at cost, margin-neutral in cash, but it dilutes the percentage from 10.0% to 9.4%. More turnover, same profit.
Months 8 & 11 · Margin hit
Glazing rates rise (+1.2M, month 8) and remedial work follows (+0.6M, month 11): QAR 1.8M over budget. Contingency is exhausted; the margin erodes to 7.7%.
Committed cost leads, actual cost lags. The forecast cost per package is MAX(committed-to-date, budget) — so an order placed today moves the outturn today, not at the final account.
Margin recalculates every month. The CVR rolls each package's forecast cost and value into a project-total forecast margin, independent of the chosen data date.
Variances flag automatically. Packages drifting beyond ±5% turn AMBER then RED on the watchlist, the façade was visible in month 8, ten months before handover.
A short reference for the quantity-surveying terms used above.