CVR·Control Open live model

Commercial cost control · Quantity surveying

Seeing the final account
before it arrives.

Every month a quantity surveyor rebuilds the same commercial report by hand. Because it looks backward, problems surface in the final account, too late to act. This project automates that report and adds a forecast-margin layer that recalculates the outturn every month, turning cost control into an early-warning system.

01

Monthly commercial report

Cost-Value Reconciliation live to the data date. Drag the reporting period to recalculate every KPI and chart. All figures QAR · synthetic.

M1 · Mobilisation M20 · Handover
M11
Month 11 of 20 Façade & MEP 55% elapsed

Contract sum turnover

QAR 53.00M

Base QAR 50.0M + variation 3.0M

Forecast cost EAC

QAR 48.92M

vs budget 48.02M

Forecast margin

QAR 4.08M

4,077,325 absolute

Forecast margin % Below target

7.69%

Target 10.00% · −2.31pp

Cost variance vs budget

−QAR 0.90M

Net of contingency draw-down

Contingency remaining

QAR 0.00M

0% of QAR 1.35M reserve

Value certified to date

QAR 29.43M

56% of contract value

Forecast margin — monthly trend

Project-total margin recalculated for every reporting month 1–20.

  • Forecast margin %
  • 10.0% target
  • Data date

S-curve — value & cost

Cumulative position to the data date.

  • Planned value
  • Value certified
  • Actual cost

Package watchlist 3

Packages forecast over budget at the current data date, worst first.

  • RED ≤ −5%
  • AMBER < 0%
PackageBudgetForecast (EAC) VarianceVar %Flag
02

The brief, and what went wrong

A synthetic project engineered to fail in three instructive ways, so the model can prove it catches them.

The model tracks a G+8 reinforced-concrete residential building in Doha: 9,500 m² GFA, 64 apartments, an 18-month programme (forecast to finish in 20), and a QAR 50M contract sum that grows to 53M after a client variation. Three problems were designed into it.

Month 2 · Absorbed

Ground-conditions delay

Substructure slips a month; +QAR 0.45M of works and extended prelims. Soaked up by contingency, so margin is untouched, the reserve does its job.

Month 7 · Dilutive

Client variation

A QAR 3.0M scope addition priced at cost, margin-neutral in cash, but it dilutes the percentage from 10.0% to 9.4%. More turnover, same profit.

Months 8 & 11 · Margin hit

Façade overrun

Glazing rates rise (+1.2M, month 8) and remedial work follows (+0.6M, month 11): QAR 1.8M over budget. Contingency is exhausted; the margin erodes to 7.7%.

How the early-warning works

A

Committed cost leads, actual cost lags. The forecast cost per package is MAX(committed-to-date, budget) — so an order placed today moves the outturn today, not at the final account.

B

Margin recalculates every month. The CVR rolls each package's forecast cost and value into a project-total forecast margin, independent of the chosen data date.

C

Variances flag automatically. Packages drifting beyond ±5% turn AMBER then RED on the watchlist, the façade was visible in month 8, ten months before handover.

03

Glossary

A short reference for the quantity-surveying terms used above.

BoQ
The priced bill of quantities, the costed list of every work item.
Valuation / IPC
The monthly payment certificate, what the client is billed for work done.
Prelims
Time-related site overheads. A delay quietly becomes cost.
Committed cost
Orders placed, a leading indicator. Actual cost lags behind it.
Contingency
A risk reserve held inside the budget to absorb the unexpected.
Retention
Cash withheld as security against defects, not margin.
EAC
Estimate at completion, the forecast final cost of the works.
CVR
Cost-value reconciliation → the forecast margin engine itself.